Work Code: 1703004083/RC/22012034184130 (सीसी पंच परमेश्‍वर बरजोर सिंह के मकान से जवाहर सिं)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 15/8/2012 Work start date : 30/10/2012
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 83/309 Sanction Date : 11/10/2012
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost MMGSY scheme2 scheme3 Total
121787 81191 0 0 563310 0 0 645000 0 766288
Financial Sanction Details
Financial\Administrative Sanction No: 83/12005 Financial\Administrative Sanction Date 23/10/2012
Fin. Sanc. Amt. (in Rs) NREGA:766288 MMGSY
0
Scheme 2
0
Scheme 3
0
Total
767000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Contingency137542.7537542.75
2Dag-beling-Single spade stroke minimum 75mm deep5200.2104
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)1952842554190
4False work for R.C.C. and P.C.C. work in plinth and foundation208124.825958.4
5Transportation of 20 MM metal165.75383.463548.55
6Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.278.85166.6646473.141
7Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN152.157.38715.33
8Collection of hard moorum including stacking at quarry.152.1118.317993.43
9Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Dense or hard soil.101411.611762.4
Total Activity 767000
S.NoMaterialQuantityUnit PriceTotal
120 MM B.T.METAL166900149400
2CEMENT(BEGS)1230268329640
3Centering and Shuttering20875.315662.4
4contangency and work charges125973.2225973.22
5SAND8470058800
6Sand Transportation84220.8618552.24
7Transportation charges of mate278.85166.6646473.141
Total Material 645000