Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 26-Sep-2024 11:45:58 PM 
Back  
State: MADHYA PRADESH District: REWA Block: GANGEV Panchayat: LALGAON
Work Code: 1713004009/RC/22012034338581 (सुदूर ग्राम संपर्क सडक भौखरी मार्ग से रेवांचल स्‍कूल तरफ )
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2017-2018 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 17/4/2017 Work start date : 19/5/2017
Present status : Earthern road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 135/09 Sanction Date : 12/5/2017
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
316000 580000 0 0 0 0 0 580000 0 896000
Financial Sanction Details
Financial\Administrative Sanction No: 4009/135/02 Financial\Administrative Sanction Date 14/5/2017
Fin. Sanc. Amt. (in Rs) NREGA:896000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
896000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Site clearance, cutting grass, raking into heaps and removing off the premises20481.73481.6
2Dag-beling-Single spade stroke minimum 75mm deep96032880
3Transportation of metal 1026.14112.41115348.3974
4Transportation of metal 306.16412.02126144.0432
5Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-600mm dia25964.424110
6Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making1388.3421.629988.144
7Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor1384.1042331834.392
8Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work1246.29687.3108801.6408
9Collection of puddle earth including stacking at quarry1626.296121.3197269.7048
10Collection of hard moorum including stacking at quarry.1404.32140.7197587.824
11SIGN BOARD160006000
12Labour difference in case of old SoR32515951675
Total Activity 896000
S.NoMaterialQuantityUnit PriceTotal
1Board120002000
2collection and transportation 16800068000
3Compaction of Earth Work14500045000
4Compaction of GSB16800068000
5Compaction of Selected soil14500045000
6contigency150005000
7earth work watring11200012000
8GITTI12500025000
9Gravel or moorum11200012000
10hume pipe np3-600mm12000020000
11roller110001000
12Rolling Earth & moorum11500015000
13Transportanion of hard Muram14500045000
14Transportation Of Earth Work1125000125000
15Transportation of GSB14500045000
16Transportation Of Selected Soi14500045000
17पानी टेंकर120002000
Total Material 580000