S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 285 | 1.5 | 427.5 |
2 | Earth work in rough excavation,filling excavated earth into depressions on banking as directed ,top surface to be levelled and neatly dressed.-Dense or hard soil | 129.375 | 81 | 10479.375 |
3 | contingency | 1 | 482 | 482 |
4 | Labour difference in case of old SoR | 1 | 1156 | 1156 |
5 | Earth work in excavation in Ordinary soil including all leads and lifts including rough dressing and breaking clods deposited the excavated materials away from work site. | 0 | 0 | 0 |