The Mahatma Gandhi National Rural Employment Guarantee Act 27-Sep-2024 05:55:14 PM 
Back  
State: MADHYA PRADESH District: KHANDWA Block: PANDHANA Panchayat: HEERAPUR RAIYAT
Work Code: 1725007034/WC/22012034543852 (जल सव्रेधन कार्या निर्भयसिंग के खेत के पास)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2020-2021 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 1/4/2020 Work start date : 25/4/2020
Present status : Non-existent Proposed Status : Wasteland Block Plantation-Horticulture-Community
Tech Sanction Details
Technical Sanction No. : 1725007/2020-2021/81109/TS Sanction Date : 4/5/2020
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
248151.19 691971.31 3366.38 13158.78 0 0 0 709000 0 956647.66
Financial Sanction Details
Financial\Administrative Sanction No: 1725007/2020-2021/81109/AS Financial\Administrative Sanction Date 4/5/2020
Fin. Sanc. Amt. (in Rs) NREGA:956648 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
957000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.6006.541953925.17
2Disintegrated or soft rock (not requiring blasting)49.23312.81799715620615400.03
3(a) C.C. 1:2:4 (1cement, 2sand, 4metal)148.443812.70115871733565957.36
4(b) C.C. 1:3:6 (1cement, 3sand, 6metal)27.813159.3685724559587862.04
5False work for R.C.C. and P.C.C. work in plinth and foundation.154.46164.44736501359625400.54
6(XX) 20 Km. Lead145320.24289655172446435.22
7(XX) 20 Km. Lead72.5288.21862068965520895.85
8(XXVII) 40 Km. Lead33438.61787878787914474.39
9a (i) Loose or soft soil for Road Work50099.406149703.05
10b (iii) Dense or hard soil for Tank Work48.15134.187538940816461.13
11c (i) Hard moorum for Road Work500178.630489315.2
12c (iii) Hard moorum for Tank Work32.55178.7376344086025817.91
Total Activity 932000
S.NoMaterialQuantityUnit PriceTotal
10002-Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper17.62588515598.125
20084-Hire charges of Diesel truck - 9 tonne (without POL)2.05922424616.278
30297-Stone Aggregate(single size): 10 mm nominal size16.328463010286.892
40367-Portland Cement55.10345511303674.8374
50983-Fine sand (zone IV)79.86871076.2585958.688375
610-Miscellaneous /Contingencies charges12000020000
71235-Diesel oil72.21684910.28
83-Display Board150005000
95001-Mobil oil2.581182.9472.0649
10MR6001-Stone Aggregate(single size): 40 mm nominal size other than BT95.265352550014.2825
11MR6082-Stone Aggregate (Metal) 20mm nominal size (BT Metal) (Rate at quarry)39.331268226823.8784
12MR6091-WOOD-Kail wood 2nd class0.579215825.69166.18752
Total Material 537000