S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Contingency | 1 | 54201 | 54201 |
3 | Work charge | 10 | 10000 | 100000 |
4 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil | 43.77 | 70.6 | 3090.162 |
5 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Hard moorum | 34.43 | 92.6 | 3188.218 |
6 | Filling foundation and around masonry work with moorum I/c ramming layers and watering. | 143.42 | 145.4 | 20853.268 |
7 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 24.74 | 2092 | 51756.08 |
8 | Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:2:4 (1cement, 2sand, 4graded stone aggregate 20 mm nominal size) | 50.58 | 3375.4 | 170727.732 |
9 | False work for lintels slabs, columns, walls, sills, chhajjas balconies, beams, stair cases or ornamental moulded work, curved surface etc. cast in situ including all lead and lift | 301.1 | 223.8 | 67386.18 |
10 | False work for R.C.C. and P.C.C. work in plinth and foundation | 140.37 | 164.1 | 23034.717 |
11 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:6 (1cement, 6sand) | 42.53 | 2823 | 120062.19 |
12 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:8 (1cement, 8sand) | 13.74 | 2715 | 37304.1 |
13 | Steel work welded in built up sections, framed work, including cutting hoisting fixing in position in gratings, frames, guard bars, ladders, railing, brackets and similar works & trusses and trussed purlins up to 25m span and 15 m over all height | 1668 | 68.2 | 113757.6 |
14 | Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars | 3464.69 | 54.4 | 188479.136 |
15 | Providing and fixing in position collapsible steel shutters with vertical channels 20mm x 10mm x 2mm braced with flat iron diagonals 20mm x 5mm size with top and bottom rails of T-iron 40mm x40mm x6mm with 38mm dia steel pulleys complete with bolts and nu | 3.78 | 3642.9 | 13770.162 |
16 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:3 (1cement, 3sand) | 580 | 129.5 | 75110 |
17 | Cement concrete flooring 1:2:4 (1cement, 2sand, 4graded stone aggregate, 20mm nominal size) laid in one layer and finished with floating coat of neat cement.-40 mm thick. | 55 | 200.5 | 11027.5 |
18 | White glazed tiles 6mm thick in flooring, treads of steps and landings laid on a bed of 12mm thick cement mortar 1:3 finished with flush pointing in white cement. | 36.4 | 733.8 | 26710.32 |
19 | Kota stone slab flooring over 20mm thick base of C.M. 1:6 laid over and jointed with grey cement slurry mixed with pigment to match the shade of slab including grinding, rubbing & polishing etc. complete. (Area of each stone should not be less than 0.20 S-25 mm thick. | 60 | 1273.9 | 76434 |
20 | Kota stone slab/Cuddapah stone slab 25mm thick in risers and treads of steps, skirting dado and pillar laid in 12mm thick C.M. 1:3 and jointed with grey cement slurry mixed with pigment to match the shade of slab including rubbing polishing etc. complete. | 5.69 | 1328.7 | 7560.303 |
21 | Cement washing (Portland cement) 2 coats.-White cement | 414.81 | 11.9 | 4936.239 |
22 | Snowcem or durocem painting of any shade-2 coats on new work | 290 | 14.1 | 4089 |
23 | Oil bound distemper of approved quality of any shade two coats on new works including priming coat. | 290 | 61 | 17690 |
24 | Painting with enamel paint, brushing, interior to give an even shade I/n cleaning the surface of all dirt dust and other foreign matter on steel and other metal surfaces.-2 coats | 109.07 | 61 | 6653.27 |
25 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 1 | 85178 | 85178 |