S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 1912.5 | 6.64523921568628 | 12709.02 |
2 | Providing stone chips under stone pitching | 337.5 | 454.87922962963 | 153521.74 |
3 | (a) Other then black trap Basalt or granite | 98.64 | 301.756893755069 | 29765.3 |
4 | (a) Consolidation of Moorum /earth work (rate for 1Cum. of Moorum /earth work) | 3080.93 | 2.38837299127212 | 7358.41 |
5 | (XI) 6 Km. Lead | 98.64 | 262.241484184915 | 25867.5 |
6 | (III) 1.5 Km. Lead | 1023.75 | 77.9294358974359 | 79780.26 |
7 | (XIV) 9 Km. Lead | 1901.25 | 200.121677843524 | 380481.34 |
8 | (XV) 10 Km. Lead | 155.93 | 210.627525171551 | 32843.15 |
9 | (a) Boulders | 94.5 | 576.088148148148 | 54440.33 |
10 | For earthen dam - puddle filling of good clay including lead upto 20 meter including mixing, watering & kneading by tamping , ramming & laying etc. | 155.93 | 428.455524915026 | 66809.07 |
11 | Hearting, casing/cut off filling soil etc.
At optimum moisture content to achieve maximum dry density by mechanical sheep foot roller/ vibratory compacters including watering, required leads and lifts and material etc. complete. | 3080.93 | 21.7850421788226 | 67118.19 |
12 | a (iii) Loose or soft soil for Tank Work | 100.74 | 100.979650585666 | 10172.69 |
13 | b (iii) Dense or hard soil for Tank Work | 1023.75 | 136.306246642247 | 139543.52 |
14 | c (iii) Hard moorum for Tank Work | 2011.05 | 181.559926406603 | 365126.09 |
15 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 127.41 | 577.40169531434 | 73566.75 |