S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Loose or soft soil | 57.32 | 76.9 | 4407.908 |
3 | Filling foundation and around masonry work with moorum I/c ramming layers and watering. | 56.25 | 158.3 | 8904.375 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 9.19 | 2603.5 | 23926.165 |
5 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 0.89 | 3474.1 | 3091.949 |
6 | Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:1:2 (1cement, 1sand, 2graded stone aggregate 20 mm nominal size) | 5.27 | 4071.3 | 21455.751 |
7 | Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Lime mortar 1:2 (1lime putty, 2sand) | 29.1 | 2216.4 | 64497.24 |
8 | Extra rate for C.R./ R.R./ U.C.R. stone masonry in super structure above plinth level upto floor two level. | 22.08 | 2436.6 | 53800.128 |
9 | Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars | 303.03 | 58.4 | 17696.952 |
10 | TRANSPORTATION OF MATERIAL | 29 | 1000 | 29000 |
11 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 27.6 | 150.6 | 4156.56 |