S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | (II) Lead upto 150 meters | 738 | 77.8005013550136 | 57416.77 |
2 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 12 | 3855.96583333333 | 46271.59 |
3 | Steel work in single section including in cutting, hoisting fixing in position in R.S. joists, channels, angles, tee. | 700 | 64.0945428571429 | 44866.18 |
4 | (VI) 3.0 Km. Lead | 738 | 163.743550135501 | 120842.74 |
5 | Labour only for boulder soling hand packed excluding consolidation. | 738 | 199.717533875339 | 147391.54 |
6 | (b) Dense or hard soil | 702 | 156.787464387464 | 110064.8 |
7 | Collection of boulders at source (maximum size 0.014cum) without quarrying i.e. picked up boulders. | 738 | 172.89 | 127592.82 |
8 | Stacking of Gravel or Hard Moorum at site without Boxing. | 738 | 23.3286178861789 | 17216.52 |
9 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1 | 3682 | 3682 |