S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete. | 28 | 638.8 | 17886.4 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 42 | 2414.7 | 101417.4 |
3 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 14 | 3194.2 | 44718.8 |
4 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Lime Mortar 1: 2(1lime, 2sand) | 70 | 2957.6 | 207032 |
5 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:3 (1cement, 3sand) | 313 | 151.8 | 47513.4 |
6 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Loose or soft soil | 294 | 96.2 | 28282.8 |