State: MADHYA PRADESH District: REWA Block: GANGEV Panchayat: KHAIRA
Work Code: 1713004014/WC/22012034912859 (Talab Jirnoddhar karya Devin Dai Talab)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2021-2022 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 26/1/2022 Work start date : 16/2/2022
Present status : Existing Proposed Status : Renovtion of Community Ponds for Comm
Tech Sanction Details
Technical Sanction No. : 14/302 Sanction Date : 8/2/2022
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Beneficiary Contribution scheme2 scheme3 Total
153000 142000 0 0 2000 0 0 144000 0 297000
Financial Sanction Details
Financial\Administrative Sanction No: 22/967 Financial\Administrative Sanction Date 11/2/2022
Fin. Sanc. Amt. (in Rs) NREGA:295000 Beneficiary Contribution
2000
Scheme 2
0
Scheme 3
0
Total
297000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Site clearance, cutting grass, raking into heaps and removing off the premises1237.056.658226.3825
2Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil403.88181.5673328.4528
3Dag-beling-Single spade stroke minimum 75mm deep3000.38114
4Extra for every additional lift of 1.5 m or part there of-Loose/soft soil and dense/hard soil242.3311.162704.4028
522cm thick dry stone pitching (without quarry spalls) with individual stone of 22cm depth and minimum size 0.014222.64370.2682434.6864
6Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 403.882.39965.2732
7Transportation rates for Boulders, Laterite, rubble pitching stones and excavated hard rock.222.64242.2853941.2192
8Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.403.88111.7545133.59
9Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making403.8821.18521.868
10FOR EARTHEN DAM - Construction of rock toe in earthen embankments including laying and hand packing, dressing, wedging and finishing over surface with.-Boulders110.96163.5718149.7272
11SIGN BOARD130003000
Total Activity 297000
S.NoMaterialQuantityUnit PriceTotal
1contigency130003000
2Loosening Machine Rent403.8820.898437.0532
3Pitching stones222.64405.91190372.02504
4Roller403.8819.627924.1256
5SIGNBOARD135303530
6Water Transportation403.880.2288.8536
7मिटटी परिवहन403.8875.5430509.0952
Total Material 144000