S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 30.38 | 2202.3 | 66905.874 |
2 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 22.78 | 3307.4 | 75342.572 |
3 | False work for R.C.C. and P.C.C. work in plinth and foundation | 67.5 | 147.8 | 9976.5 |
4 | Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:8 (1cement, 8sand) | 101.25 | 2082.1 | 210812.625 |
5 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 270 | 127.6 | 34452 |
6 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 98 | 960.2 | 94099.6 |
7 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 52.7 | 96.2 | 5069.74 |