S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 800 | 4.4 | 3520 |
2 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 2280 | 23.9 | 54492 |
3 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 2280 | 31.2 | 71136 |
4 | FOR EARTHEN DAM - Benching the seat of embankment over to an average depth of 15cm and cross slope of 1:12 including earth work removing the rubbish upto a distance of 50m including dressing. | 120 | 117.2 | 14064 |
5 | Earth work in rough excavation,filling excavated earth into depressions on banking as directed ,top surface to be levelled and neatly dressed.-Dense or hard soil | 2280 | 97.6 | 222528 |
6 | contingency | 1 | 14000 | 14000 |