S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 3200 | 1.6 | 5120 |
2 | Work charge | 12000.68 | 13.5 | 162009.18 |
3 | Dag-beling-Single spade stroke minimum 75mm deep | 1500 | 0.2 | 300 |
4 | Transportation of metal | 919 | 92.1 | 84639.9 |
5 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 1780 | 23 | 40940 |
6 | Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP: | 175 | 578.3 | 101202.5 |
7 | Earth work for well excavation-Lift from 7.50 m. to 8.00 m. | 1119 | 191.6 | 214400.4 |
8 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed. | 1945 | 81.2 | 157934 |
9 | Collection of puddle earth including stacking at quarry | 459 | 112.8 | 51775.2 |
10 | 1902 Transportion of metal | 1 | 170000 | 170000 |
11 | SIGN BOARD | 1 | 1500 | 1500 |