S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Cutting down trees (exceeding 30cm girth, grubbing uproot, filling pits and levelling off ground, lopping branches, trimming, removing not exceeding 50meter & staking serviceable material and cleaning site.-Girth exceeding 100 cm and not exceeding 150 cm | 71 | 1000 | 71000 |
2 | Cutting down trees (exceeding 30cm girth, grubbing uproot, filling pits and levelling off ground, lopping branches, trimming, removing not exceeding 50meter & staking serviceable material and cleaning site.-Girth exceeding 150 cm and not exceeding 200 cm | 3906.8 | 11.15 | 43560.82 |
3 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil | 167.5 | 163.19 | 27334.325 |
4 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring blasting | 699.98 | 209.34 | 146533.8132 |
5 | Earth work in rough excavation, filling excavated earth into depressions on banking as directed, top surface to be levelled and neatly dressed.-Loose or soft soil | 10 | 280 | 2800 |
6 | Excavation in trenches for foundations and for pipes, cables, etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms, lift upto 1.5m including getting out and-Hard rock requiring blasting | 3908.6 | 11.15 | 43580.89 |
7 | Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Hard Moorum | 0 | 0 | 0 |