Asset Register
|
Work Name
|
(2404051015/WC-M.I.P./81963) COMPL. OF HATIAPATHAR CIP |
Nature of Work |
Water Conservation
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Non-existent |
Feeder Channel |
|
Location
|
Start Location |
KAPANDA |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: FS-1056 ,
25/08/2008
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
5
|
Estimated Completion Time (in Months)
|
3 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
122974.98 |
0 |
0 |
377037.04 |
0 |
500012.02 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
816 |
136 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
15978(7200),15979(7200),15980(7200),15981(7200),15982(7200), 15983(7200),15984(7200),15985(7200),15986(7200),15987(7200), 15988(7200),15989(7200),15990(7200),15991(7200),15992(7200), 15996(7200),15997(7774.98),
|
Work start date |
11/11/2009 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|