Asset Register
|
Work Name
|
(2005001026/IC/1056) Construction of drain at Nilababu Leirak |
Nature of Work |
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Existing |
Construction of Canal, Distributary and Minor |
|
Location
|
|
Sanction No. and Sanction Date
: 1/SAP/-GP/NREGS/SO/2 ,
16/07/2011
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
3.35467
|
Estimated Completion Time (in Months)
|
0.6 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
229068 |
0 |
0 |
102900 |
0 |
331968 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1818 |
202 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
31528(17640),31529(17640),31530(17640),31531(17640),31532(17640), 31533(17640),31534(17640),31535(17640),31536(17640),31537(17640), 31538(1764),31539(5040),31540(5040),31541(5040),31542(5040), 31543(5040),31544(5040),31545(5040),31546(5040),31547(5040), 31548(5040),31549(504),
|
Work start date |
17/08/2011 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|