Asset Register
|
Work Name
|
(1404003008/RC/8808634036) Const of devaskoot Road from M/R to to site Ab rahid Mir onwards with Slab of Bardaji and Spun pipes |
Nature of Work |
Rural Connectivity
|
|
On Going
|
Scope of Work
|
Start Status |
End Status |
Earthern road |
Construction of Bitumen Top Roads for Community |
|
Location
|
Start Location |
End Location |
|
Chewedara Partly |
Khata No. |
Plot No. |
/ |
/ |
|
Sanction No. and Sanction Date
: 1404016/2023-2024/153990/AS ,
03/10/2023
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
2.48091
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
152256 |
0 |
0 |
0 |
0 |
152256 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
624 |
72 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
2387(16104),2388(13176),2389(10980),2390(9028),4131(34160), 4132(26352),4858(24400),4859(16104),7244(1952),
|
Work start date |
10/11/2023 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|