Asset Register
|
Work Name
|
(2717004200/IF/2176) बेरी निर्माण कालु / राणा मुसलमान |
Nature of Work |
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Not Exist |
Well |
|
Location
|
|
Sanction No. and Sanction Date
: 2616. ,
23/03/2011
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
2
|
Estimated Completion Time (in Months)
|
6 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
122874 |
0 |
0 |
56453.5 |
0 |
179327.5 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1244 |
110 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
334803060(300),1770(8568),99000248(10800),99001964(2450),99004460(4284), 99008656(3900),99011881(8400),99019776(7225),99021105(2800),99024936(5920), 99025576(9163),99027228(8568),99030026(10780),9974(16250),9975(9906), 25397(13860),
|
Work start date |
24/03/2011 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|
MB Book Detail
|