Asset Register
|
Work Name
|
(3506002022/AV/2008051090) कुण्डलपुर तोक में पुलिया निर्माण देवर क्रं0सं0 521 |
Nature of Work |
|
Work Status
|
Completed
|
Work Purpose status
|
Constr of Culvert/cross drainage work for Comm |
Scope of Work
|
|
Sanction No. and Sanction Date
: 3506002022/2020-2021/61955/AS ,
19/08/2020
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
1.99833
|
Estimated Completion Time (in Months)
|
11.57 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
82008 |
21200 |
0 |
55923 |
0 |
159131 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
408 |
31 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
3467(14070),3814(23919),4138(21105),4449(22914),
|
Work start date |
21/08/2020 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|