Asset Register
|
Work Name
|
(0504007017/WC/20335564) duari tansafarmar se lekar ciksil siwan tak ahar kuday |
Nature of Work |
Water Conservation
|
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Existing |
Construction of Earthen graded Bund for Community |
|
Location
|
Start Location |
Duari |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: 0504007017/2019-2020/71334/AS ,
18/09/2019
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
5.42326
|
Estimated Completion Time (in Months)
|
3.6 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
525934 |
0 |
0 |
4500 |
0 |
530434 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2711 |
254 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
2921(27160),2922(21728),2932(22698),2933(25220),2934(7566), 3022(21340),3023(21340),3024(8536),3957(12610),3958(10088), 3959(20176),3960(10088),3961(12610),3962(25220),3963(25220), 3964(25220),3965(25220),4071(21340),4072(14938),4073(14938), 4514(13580),4515(13386),4988(13968),4990(15520),4991(13968), 4992(13968),4993(15520),4994(15520),4996(15520),4999(7760), 5000(13968),
|
Work start date |
26/05/2020 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|