Asset Register
|
Work Name
|
(2311001017/AV/16516) extension of village connecting road PH - II |
Nature of Work |
|
Work Status
|
On Going
|
Scope of Work
|
|
Sanction No. and Sanction Date
: 2311004/2023-2024/4269/AS ,
04/12/2023
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
8.1659
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
489888 |
0 |
0 |
0 |
0 |
489888 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2187 |
243 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
5216(38304),5217(38304),5218(38304),5219(38304),5220(38304), 5221(38304),5222(38304),5223(38304),5224(38304),5225(38304), 5226(38304),5227(38304),5228(30240),
|
Work start date |
01/12/2023 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|