Asset Register
|
Work Name
|
(2430002014/RC/3089943) CONST OF NEW ROAD FROM BADASAHI TO DHARINIGUDI |
Nature of Work |
Rural Connectivity
|
Work Status
|
Completed
|
Work Purpose status
|
Metal First coat |
Scope of Work
|
Start Status |
End Status |
Earthern road |
Metal First coat |
|
Location
|
Start Location |
End Location |
|
SIRSIAGUDA |
Khata No. |
Plot No. |
NA/NA |
NA /NA |
|
Sanction No. and Sanction Date
: 3830-khg-17/18 ,
04/12/2017
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
5
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
330176 |
0 |
0 |
157545 |
0 |
487721 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1876 |
148 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
17063(23936),17064(16368),17065(23232),17066(21472),17067(22176), 17068(6688),18262(21120),18263(24288),18264(23936),18265(21472), 18266(1584),24068(12320),24069(13904),24070(28160),24071(28160), 24072(25344),24073(16016),
|
Work start date |
16/01/2018 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|