Asset Register
|
Work Name
|
(3401017004/IF/7080901111819) (1617106W57)मनोरंजन महतो के जमीन पर सिचाई कूप निर्माण |
Nature of Work |
|
Work Status
|
Completed
|
Work Purpose status
|
DUGWELLS |
Scope of Work
|
Start Status |
End Status |
Not Exist |
DUGWELLS |
|
Location
|
|
Sanction No. and Sanction Date
: 1317 ,
16/11/2016
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
3.51
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
113904 |
0 |
0 |
124444 |
0 |
238348 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
720 |
130 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
455(10080),1144(8064),2141(10080),2142(3024),3315(9072), 3316(6048),3817(10080),3818(5040),4702(10080),4703(3024), 5866(8064),5867(5040),6628(168),6629(168),6630(168), 8453(10080),8454(4032),9055(168),9056(168),14036(7056), 14037(2016),14549(168),15411(168),19895(168),19992(168), 4756(168),5080(7056),5340(1008),6779(168),7472(168),
|
Work start date |
22/03/2017 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|