Asset Register
|
Work Name
|
(2412007006/WC-Tank/38555) Chikiti/Ganjam Reno of BeniaTank at Liakhai |
Nature of Work |
Water Conservation
|
Work Status
|
Completed
|
Work Purpose status
|
Desilting |
Scope of Work
|
Start Status |
End Status |
Silted |
Desilting |
|
Location
|
|
Sanction No. and Sanction Date
: 402/2008 ,
01/01/2008
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
2
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
141251 |
0 |
0 |
9288 |
0 |
150539 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2665 |
264 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
120311(4872),120312(6960),120313(5568),120314(6960),120315(5136), 120316(5280),120317(7200),120318(5640),120319(6480),120320(2880), 120321(1302),120322(2170),120323(1953),120324(1953),120325(1519), 134255(6240),134256(6000),134257(5250),134258(5400),134259(5400), 134260(6024),134261(5760),134262(4944),134263(6360),134264(8160), 134265(3300),134266(3300),134267(2970),134268(2970),134269(3300),
|
Work start date |
23/02/2008 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|