Asset Register
|
Work Name
|
(1206004/IC/1000026322) Clearance of Jungle from internal section of Naraina Drain from RD 0 to 39000 (2022-23) |
Nature of Work |
|
|
On Going
|
Scope of Work
|
Start Status |
End Status |
Existing |
Renovation of distributary Canal for Community |
|
Location
|
|
Sanction No. and Sanction Date
: 595.1 ,
13/05/2022
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
5.61
|
Estimated Completion Time (in Months)
|
6 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
159211 |
0 |
0 |
0 |
0 |
159211 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
481 |
38 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
248(43692),249(38065),426(41706),427(35748),
|
Work start date |
09/06/2022 |