Asset Register
|
Work Name
|
(2412016022/RC-Sand Moram/122722) Const of road from main road to Puriasahi |
Nature of Work |
Rural Connectivity
|
|
Completed
|
Work Purpose status
|
Sand Moram |
Scope of Work
|
Start Status |
End Status |
Earthern road |
Sand Moram |
|
Location
|
Start Location |
End Location |
|
PURIASAHI |
Khata No. |
Plot No. |
0/0 |
0/0 |
|
Sanction No. and Sanction Date
: 956/2010 ,
26/10/2010
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
5
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
6488 |
0 |
6488 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1369 |
241 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
577559(5310),577560(5220),577561(5310),577562(5400),577563(2700), 577564(5400),577565(5310),577566(5220),577567(5220),577568(2520), 577569(5400),577570(5400),577571(5220),577572(5040),577573(5400), 577574(5400),601117(2790),601118(5220),601119(4140),601120(4590), 601121(5220),601122(5130),601123(4500),601124(4500),601125(4050), 601126(3600),
|
Work start date |
18/12/2010 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|