Asset Register
|
Work Name
|
(3302002113/AV/1111457167) दुर्जनपुर - लिलादादर पुलिया निर्माण कार्य पकरीनाला में ख.न. 44 रकबा 0.625हें. |
Nature of Work |
|
Work Status
|
Completed
|
Work Purpose status
|
Constr of Culvert/cross drainage work for Comm |
Scope of Work
|
|
Sanction No. and Sanction Date
: 97/23-24 ,
16/05/2023
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
15.43
|
Estimated Completion Time (in Months)
|
3 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
304538 |
0 |
0 |
1127996.58 |
0 |
1432534.58 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1378 |
277 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
25081(10608),25082(10608),25083(11050),25084(884),29212(13260), 29213(13260),29214(11713),29215(13260),29216(6630),32797(11050), 32798(11050),32799(11050),32800(11050),32801(5967),32898(2210), 36066(13039),36067(13039),36068(13039),36069(13039),36070(11713), 38454(13260),38455(13260),38456(10608),38602(6630),38603(6630), 38604(6630),38605(1326),38671(9282),38672(8619),38673(9282), 38674(5304),39137(6188),
|
Work start date |
31/05/2023 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|