Asset Register
|
Work Name
|
(2004003015/LD/6847) Land Development including Supply Canal |
Nature of Work |
|
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Not Exist |
Reclamation of Land |
|
Location
|
|
Sanction No. and Sanction Date
: 16ckg266 ,
21/06/2016
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
7.72
|
Estimated Completion Time (in Months)
|
10 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
612670 |
0 |
0 |
243813 |
0 |
856483 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
3110 |
413 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
291(324065),292(125489),1165(163116),
|
Work start date |
05/09/2016 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|