Asset Register
|
Work Name
|
(2412001002/DP/10348027) PLANTATION FROM RANIBANDHA TO BALUNKESWAR TEMPLE |
Nature of Work |
Drought Proofing
|
Work Status
|
Completed
|
Work Purpose status
|
Block Plantation of Forestry-in Fields-Community |
Scope of Work
|
Start Status |
End Status |
Not Exist |
Block Plantation of Forestry-in Fields-Community |
|
Location
|
Start Location |
NUA BABANPUR |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: 123/3214 ,
11/07/2018
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
0.86
|
Estimated Completion Time (in Months)
|
12 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
78 |
13 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
5727(8736),5728(1092),6799(1092),6902(3276),
|
Work start date |
26/07/2018 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|