Asset Register
|
Work Name
|
(1613001003/LD/512526) ഇടപ്പാളയം വാര്ഡില് തട്ടുതിരിക്കല് പ്രവൃത്തികള് ഭാഗം-8 |
Nature of Work |
|
Work Status
|
On Going
|
Work Purpose status
|
Constr of Level Bench Terrace Terrace for Comm |
Scope of Work
|
Start Status |
End Status |
Existing |
Constr of Level Bench Terrace Terrace for Comm |
|
Location
|
|
Sanction No. and Sanction Date
: 1613001003/2023-2024/265503/AS ,
25/10/2023
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
1.96639
|
Estimated Completion Time (in Months)
|
0.7 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
110889 |
0 |
0 |
0 |
0 |
110889 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
333 |
87 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
39365(10656),39366(14985),39367(12654),39368(11655),39369(10656), 39370(13320),43813(9657),43814(8991),43815(12321),43816(1665), 43817(1998),43818(2331),
|
Work start date |
01/04/2023 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|