Asset Register
|
Work Name
|
(1422001072/IF/8808798050) Ten compost pits at Nowgam |
Nature of Work |
|
Work Status
|
On Going
|
Scope of Work
|
Start Status |
End Status |
Not Exist |
Construction of Soak Pit for Individual |
|
Location
|
|
Sanction No. and Sanction Date
: 1422003/2023-2024/119489/AS ,
07/08/2023
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
4.22923
|
Estimated Completion Time (in Months)
|
1.07 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
181292 |
0 |
0 |
211200.71 |
0 |
392492.71 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
743 |
52 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
12411(35136),12412(11712),15320(22448),21787(39040),21788(15616), 22671(32696),22672(18300),22965(6344),
|
Work start date |
09/08/2023 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|