Asset Register
|
Work Name
|
(2404051/LD/10643144) LAND DEVELOPMENT OF TIKARPADA VILLAGE(5Ha.)2021-22 PATCH-3 |
Nature of Work |
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Not Exist |
Levelling/shaping of Wasteland Land for Community |
|
Location
|
|
Sanction No. and Sanction Date
: 5636 ,
07/08/2021
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
1.89885
|
Estimated Completion Time (in Months)
|
36 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
783 |
131 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
20546(10320),20547(9030),20548(11610),20549(6450),21614(12255), 21615(10320),21616(12900),21617(9030),22493(11610),22494(11610), 22495(11610),22496(12900),23140(12900),23141(11610),23142(11610), 23143(2580),
|
Work start date |
29/04/2022 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|