Asset Register
|
Work Name
|
(2105014532/RC/51614) Extension of CC road from Upper Damachiga to Lower Damachiga at Damachiga VEC |
Nature of Work |
Rural Connectivity
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Cement concrete |
Constr of Cement Concrete Roads for Comm |
|
Location
|
Start Location |
End Location |
|
DAMACHIGA |
Khata No. |
Plot No. |
/ |
/ |
|
Sanction No. and Sanction Date
: TBA_238 ,
24/08/2020
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
9.2728
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
483140 |
0 |
0 |
444115 |
0 |
927255 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2380 |
238 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
5224(28420),5225(28420),5226(28420),5227(28420),5228(28420), 5229(28420),5230(28420),5231(28420),5232(28420),5233(28420), 5234(28420),5235(25578),6821(12180),6822(12180),6823(12180), 6824(12180),6825(12180),6826(12180),6827(12180),6828(12180), 6829(12180),6830(12180),6831(12180),6832(10962),
|
Work start date |
07/09/2020 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|