Asset Register
|
Work Name
|
(2105014605/LD/5620) Land Development with retaining wall at Bolsaldamgre Paddy Field |
Nature of Work |
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Not Exist |
Reclamation of Land |
|
Location
|
|
Sanction No. and Sanction Date
: TBA..89 ,
14/06/2017
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
6.5067
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
358750 |
0 |
0 |
250016 |
0 |
608766 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2050 |
164 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
1477(24500),1478(24500),1479(24500),1480(24500),1481(2450), 7157(22750),7158(22750),7159(22750),7160(22750),7161(2275), 7930(24500),7931(24500),7932(24500),7933(24500),7934(2450), 8983(15750),8984(15750),8985(15750),8986(15750),8987(1575),
|
Work start date |
05/07/2017 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|