Asset Register
|
Work Name
|
(2430009/RC-Earthern road/93472) Constn. of new road from dangarpara to Junapani. |
Nature of Work |
Rural Connectivity
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
No Road |
Earthern road |
|
Location
|
Start Location |
End Location |
|
KURSHI |
Khata No. |
Plot No. |
NA/NA |
NA/NA |
|
Sanction No. and Sanction Date
: 3842-UKT14-09/10 ,
27/12/2009
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
3.5
|
Estimated Completion Time (in Months)
|
3 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
87120 |
0 |
0 |
31568 |
0 |
118688 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2247 |
375 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
265051(12960),265052(12960),265053(12960),265054(12960),265055(12960), 265056(12960),265057(9360),265058(9720),265059(9720),265060(9720), 265061(9720),265062(9720),265063(9720),265064(9720),265065(9720), 265066(9720),265067(9720),265068(9720),265069(9720),265070(9720), 265071(9720),265072(810),
|
Work start date |
21/03/2010 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|