Asset Register
|
Work Name
|
(2430007/IC/10485722) CONST OF EARTHEN CANAL AT BUTIAGUDA(AAP-21-22) |
Nature of Work |
|
WorkStatus
|
Completed
|
Work Purpose status
|
Construction of distributary Canal for Community |
Scope of Work
|
Start Status |
End Status |
Not Exist |
Construction of distributary Canal for Community |
|
Location
|
|
Sanction No. and Sanction Date
: 2430007/2021-2022/15994/AS ,
23/03/2022
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
5
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
450660 |
0 |
4928 |
0 |
0 |
455588 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2030 |
320 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
2816(15540),2817(15540),2818(15540),2819(15540),2820(15540), 5071(15540),5072(15540),5073(15540),5074(15540),5075(10878), 5076(13986),5077(13986),5078(15540),5079(10878),5080(9324), 7422(15540),7423(13986),7424(15540),7425(15540),7426(15540), 7427(4662),11202(15540),11203(15540),11204(15540),11205(13986), 11206(3108),21333(10656),21335(13320),21336(9990),21337(13320), 21338(1332),21339(7548),21341(8436),21342(5328),21343(10878), 21344(10878),
|
Work start date |
19/04/2022 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|