Asset Register
|
Work Name
|
(2430009006/RC-Sand Moram/128065) IMP OF ROAD FROM BADAGAPARA TO KARLIPADAR,METALING AND COLBERT(3NO) |
Nature of Work |
Rural Connectivity
|
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Metal First coat |
Sand Moram |
|
Location
|
Start Location |
End Location |
|
BADAGAM |
Khata No. |
Plot No. |
NA/NA |
NA/NA |
|
Sanction No. and Sanction Date
: 4792-UKT19-10/11 ,
31/08/2010
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
5
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
127776 |
0 |
0 |
306957.93 |
0 |
434733.93 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1016 |
176 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
363744(7500),363745(7500),363746(7500),363747(7500),3660(7560), 3661(7560),3662(7560),3663(7560),3664(7560),3665(7560), 3666(7560),4711(7560),4712(7560),4713(7056),4714(6300), 4715(6300),4716(6300),4717(3780),
|
Work start date |
31/08/2010 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|