 Asset Register 

Work Name

(1125001027/DP/GIS/46550) Talav pal / canal line plantation work at village Munsad 

Nature of Work

Drought Proofing

Work Status

Completed

Work Purpose status

Canal Line Plantation of Forestry-Community

Scope of Work

Start Status End Status
Not Exist Canal Line Plantation of Forestry-Community

Location

Start Location Munsad
Khata No. Plot No.

Sanction No. and Sanction Date : 1125001/2021-2022/131674/AS ,  15/08/2021

Whether Included in Five Year Perspective Plan : No

 

Whether Work Approved in Annual Plan : No  

Estimated Cost (In Lakhs) : 1.49145  

Estimated Completion Time (in Months)

Expenditure Incurred (in Rs.)

Unskilled Semi-Skilled Skilled Material Contingency Total
124831  0  0  8500  133331 
Employment Generated
  Pesrondays Total No. of Persons Given Work
Unskilled 540 110
Semi-Skilled 0 0
0 0

Distinct Number of Muster Rolls used(Amount)

1763(9600),4582(13340),4583(13800),5681(9660),5682(7590),
6305(9660),6306(5520),6307(7820),6308(8280),6309(5520),
6843(9560),6844(10994),6845(5497),6846(2390),1566(5600),
 

Work start date

25/08/2021 
Photo Uploaded of Work
Before Start of Work(Work Site) During Execution of Works Completed Work
Photo Not Available Photo Not Available Photo Not Available