Asset Register
|
Work Name
|
(2401003/AV/10492638) Construction of Boundarywall at Udit Pratap Singh High School Chhamunda |
Nature of Work |
|
Work Status
|
On Going
|
Scope of Work
|
|
Sanction No. and Sanction Date
: 2401003/2022-2023/84021/AS ,
17/06/2022
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
9.82056
|
Estimated Completion Time (in Months)
|
11 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
173160 |
0 |
24752 |
635968.7407 |
0 |
833880.7407 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
780 |
130 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
5120(13320),5121(3996),5122(13320),5123(3996),5124(13320), 5125(3996),5126(13320),5127(3996),6185(13320),6186(13320), 6187(7992),6188(13320),6189(13320),6190(7992),6191(13320), 6192(13320),6193(7992),
|
Work start date |
01/07/2022 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|