Asset Register
|
Work Name
|
(1420002001/IF/8808580734) Construction of 10 numbers individual Twin Compost pits phase 10 at Anderwan A |
Nature of Work |
|
|
On Going
|
Scope of Work
|
Start Status |
End Status |
Not Exist |
Construction of Compost Pit for Individual |
|
Location
|
|
Sanction No. and Sanction Date
: 1420002/2022-2023/131055/AS ,
27/08/2022
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
0.99177
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
55161 |
9750 |
0 |
1444 |
0 |
66355 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
259 |
32 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
1444(18160),1445(16344),1446(18160),3938(2270),4613(1816), 4614(2043),
|
Work start date |
25/09/2022 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|