Asset Register
|
Work Name
|
(0316007003/IC/5126) C/o MIC from Taarik Saku to Pakga Poriang |
Nature of Work |
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Not Exist |
Construction of distributary Canal for Community |
|
Location
|
|
Sanction No. and Sanction Date
: KD/P/4 ,
25/06/2020
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
10
|
Estimated Completion Time (in Months)
|
12 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
485235 |
0 |
0 |
354680 |
0 |
839915 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2367 |
180 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
202146(115005),202148(166460),202168(203770),
|
Work start date |
05/02/2021 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|