Asset Register
|
Work Name
|
(2105014589/RC/67456) Construction of RCC Culvert at Pedaldoba Garo VEC |
Nature of Work |
Rural Connectivity
|
Work Status
|
On Going
|
Scope of Work
|
Start Status |
End Status |
Cement concrete |
Constr of Cement Concrete Roads for Comm |
|
Location
|
Start Location |
End Location |
|
PEDALDOBA (GARO) |
Khata No. |
Plot No. |
/ |
/ |
|
Sanction No. and Sanction Date
: 2105014/2021-2022/2143/AS ,
03/02/2022
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
9.00906
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
524320 |
0 |
17920 |
357830.1 |
0 |
900070.1 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2320 |
232 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
15387(31640),15388(31640),15389(31640),15390(31640),15391(31640), 15392(31640),15393(31640),15394(31640),15395(31640),15396(31640), 15397(31640),15398(18984),16387(13560),16388(13560),16389(13560), 16390(13560),16391(13560),16392(13560),16393(13560),16394(13560), 16395(13560),16396(13560),16397(13560),16398(8136),
|
Work start date |
07/02/2022 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|