Asset Register
|
Work Name
|
(1310005196/FP/8000077315) C/o Suraksha Diwar Link Road Baag Vilog Jiwani , GP Shamra |
Nature of Work |
Flood Control
|
|
On Going
|
Scope of Work
|
Start Status |
End Status |
Weak Embankment |
Construction of Embankment for community |
|
Location
|
Start Location |
Garari |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: 1310005196/2019-2020/26123/AS ,
20/03/2020
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
5.09663
|
Estimated Completion Time (in Months)
|
7.03 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
258848.74 |
0 |
0 |
184080 |
0 |
442928.74 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1305 |
99 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
140(27640.2),312(31553.6),495(25740),1492(27582.94),1630(35838), 2417(28324),3542(20196),3847(17820),499(23166),5477(20988),
|
Work start date |
01/05/2020 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|