Asset Register
|
Work Name
|
(2430007/RC/2345318) CONST OF ROAD FROM JHADKUSUMI TO NUAGUDA WITH CULV |
Nature of Work |
Rural Connectivity
|
Work Status
|
Completed
|
Work Purpose status
|
Bitumen Top |
Scope of Work
|
Start Status |
End Status |
00 |
Bitumen Top |
|
Location
|
Start Location |
End Location |
|
JHADAKUSUMI |
Khata No. |
Plot No. |
/ |
/ |
|
Sanction No. and Sanction Date
: 934-PPD-12/13 ,
21/02/2013
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
5
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
150764 |
0 |
0 |
53123 |
0 |
203887 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1059 |
198 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
11944(7308),11945(7308),11946(7560),11947(2268),1136(8580), 1137(8580),1138(8580),1139(8294),1140(429),1646(4290), 1647(4290),1648(4290),1649(3861),2430(8580),2431(6864), 2432(8580),2433(7436),9149(7722),9150(7722),9151(7722), 1374(9840),1375(7872),1376(2788),
|
Work start date |
15/03/2013 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|