Work Name
|
(2430006/RC-Metal Second coat/131715) IMPV. OF ROAD FROM MAJHIGUDA PROJECT ROAD TO BAMAN |
Nature of Work |
Rural Connectivity
|
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Bitumen Top |
Bitumen Top |
|
Location
|
Start Location |
End Location |
|
MAJHIGUDA |
Khata No. |
Plot No. |
NA/NA |
NA/NA |
|
Sanction No. and Sanction Date
: 6180-NND3-10/11 ,
14/12/2010
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
10
|
Estimated Completion Time (in Months)
|
3 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
239375 |
0 |
2244 |
752161.145 |
0 |
993780.145 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1915 |
296 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
186045(15750),186047(15750),186048(15750),186049(15750),186050(15750), 186051(14000),186052(15750),186053(10625),186054(15750),186152(6250), 186153(7500),186154(7500),186155(6000),186182(7500),186183(7500), 186184(7500),186185(7500),186186(7500),186187(7500),186188(7500), 186460(7000),186461(7500),186462(7250),186463(3000),
|
Work start date |
21/06/2011 |