Asset Register
|
Work Name
|
(2717003124/WC/112908155911) चिडानाडा खुदाई मय आगोर सुधार कार्य |
Nature of Work |
Water Conservation
|
|
Completed
|
Work Purpose status
|
Farm Pond |
Scope of Work
|
Start Status |
End Status |
Non-existent |
Farm Pond |
|
Location
|
|
Sanction No. and Sanction Date
: 10695/7 ,
16/12/2015
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
14.58
|
Estimated Completion Time (in Months)
|
12 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
121760 |
0 |
9312 |
0 |
0 |
131072 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
3382 |
351 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
55933(300),2480(2400),2481(2400),2482(2360),2483(2400), 2484(2360),2485(2040),2486(2400),2487(2400),2488(2400), 2489(2160),2490(2280),2491(1440),5588(3360),5589(3480), 5590(3480),5591(3390),5592(3540),5593(3330),5594(3150), 5595(3450),5596(3450),5597(3510),5598(3450),5599(3150), 9662(4200),9663(4440),9664(4720),9665(4480),9666(4800), 9667(4160),9668(4320),9669(4800),9670(4800),9671(4800), 9672(4800),9673(3360),
|
Work start date |
04/03/2016 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|
MB Book Detail
|