Asset Register
|
Work Name
|
(1408007007/RC/8808528101) Extension of Foot Path at Yokma Parkachik |
Nature of Work |
Rural Connectivity
|
Work Status
|
Completed
|
Scope of Work
|
|
Sanction No. and Sanction Date
: 1408007/2019-2020/8787/AS ,
04/03/2020
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
8.70099
|
Estimated Completion Time (in Months)
|
2.67 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
170667 |
0 |
0 |
121363 |
0 |
292030 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
903 |
129 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
852(56889),853(56889),854(56889),
|
Work start date |
01/02/2020 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|