Asset Register
|
Work Name
|
(2407003015/RC/10450971) IMP OF ROAD FROM LAULAI DARASAHI TO RD ROAD |
Nature of Work |
Rural Connectivity
|
Work Status
|
On Going
|
Scope of Work
|
Start Status |
End Status |
Earthern road |
Construction of Mitti Murram Roads for Community |
|
Location
|
Start Location |
End Location |
|
Laulai |
Khata No. |
Plot No. |
/ |
/ |
|
Sanction No. and Sanction Date
: 2407003/2020-2021/53540/AS ,
23/03/2021
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
8.07924
|
Estimated Completion Time (in Months)
|
1.6 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
380429 |
0 |
0 |
323161.2307 |
0 |
703590.2307 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1801 |
302 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
35518(8694),35519(2484),7830(12900),7831(11610),7832(12685), 7833(12470),9874(12900),9875(12900),9876(1290),11070(12040), 11071(12900),11072(12900),11073(6450),11420(12900),11421(12900), 11422(12900),11423(6450),16575(12900),16576(12900),16577(2580), 16600(12900),16601(12900),16602(2580),17280(12900),17281(11610), 17282(12900),17283(12685),17284(5160),18270(9030),18271(3870), 18272(6450),18273(9030),18274(2580),18275(12900),18276(12900), 18277(5160),19251(12900),19252(5160),19253(12255),19254(5160),
|
Work start date |
25/03/2021 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|