Asset Register
|
Work Name
|
(2404044028/RC/10444181) Impt.of Road from Giridhari Behera House toPuranaani Jungle |
Nature of Work |
Rural Connectivity
|
Work Status
|
Completed
|
Work Purpose status
|
Construction of Mitti Murram Roads for Community |
Scope of Work
|
Start Status |
End Status |
Earthern road |
Construction of Mitti Murram Roads for Community |
|
Location
|
Start Location |
End Location |
|
TALAPADA |
Khata No. |
Plot No. |
/ |
/ |
|
Sanction No. and Sanction Date
: 2404044/2020-2021/384003/AS ,
24/12/2020
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
2.5
|
Estimated Completion Time (in Months)
|
11.67 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
190554 |
0 |
12528 |
4000 |
0 |
207082 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
918 |
161 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
38337(12420),38338(11178),38339(6210),38341(8280),38342(7452), 38343(4140),39701(12420),39702(12420),39703(1242),40489(12420), 40490(12420),40491(12420),40493(12420),40494(12420),40495(9936), 42584(12420),42585(12420),42586(3726),3048(7740),3050(6450),
|
Work start date |
06/01/2021 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|