Asset Register
|
Work Name
|
(2404066/WC-Tank/18433) Improvement of Tank at Hatsahi Nadiathul (Rvised) |
Nature of Work |
Water Conservation
|
Work Status
|
Completed
|
Work Purpose status
|
Desilting |
Scope of Work
|
Start Status |
End Status |
Silted |
Desilting |
|
Location
|
|
Sanction No. and Sanction Date
: FS/WC-Tank-56 ,
28/01/2007
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
0.9
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
88320 |
0 |
0 |
1680 |
0 |
90000 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
840 |
70 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
6601497(10080),6601498(10520),6601499(9410),6601500(8150),6601501(11300), 6601502(15020),6601503(10410),6601504(13430),
|
Work start date |
01/03/2007 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|